Issue - meetings

Replacement of boilers at Thornton Little Theatre

Meeting: 24/08/2017 - Portfolio Holder Decisions (Item 1.)

1. Replacement of boilers at Thornton Little Theatre pdf icon PDF 107 KB

Report of the Service Director Performance and Innovation.

Decision:

On 17 August 2017 the Service Director Performance and Innovation submitted a report seeking the Resources Portfolio Holder’s approval to replace boilers at Thornton Little Theatre and to include the scheme in the Council’s 2017/18 Capital Budget.

 

Decision taken

 

The Resources Portfolio Holder gave approval to carry out the replacement of boilers with the cost of £30,000 being met from capital receipts and that the scheme be added to the Council’s 2017/18 Capital Budget.