Decision Maker: Portfolio Holder Decisions
Is Key decision?: No
Is subject to call in?: Yes
The Corporate Director Communities submitted a report seeking the approval for the provision of a temporary pavilion with associated works at King George V Playing Fields in Fleetwood, following a deliberate fire on 28 September 2020 which destroyed the previous facility.
Decision
The Resources Portfolio Holder agreed:
· That approval is given to utilise £90,000 currently held in the Insurance Reserve for the provision of a temporary pavilion and associated installation works at King George V Playing Fields, Fleetwood.
· Approval is given to retain the remaining unspent monies with the Insurance Reserve (£212,995) as match funding for any future external funding bid that may be approved.
Publication date: 23/11/2023
Date of decision: 23/11/2023
Decided at meeting: 23/11/2023 - Portfolio Holder Decisions
Effective from: 01/12/2023
Accompanying Documents: