Decision: The Chief Executive submitted a report seeking approval for the engagement of the engineering consultancy partnership Fairhurst as the council’s consultants to work as part of the Development Management Team when required, to discharge and monitor the requirements set out in the Development Consent Order granted on 17 July 2015 for the Halite Gas Storage Project, an underground gas storage facility at Preesall.
Decision taken
The portfolio holder gave approval to enter into a contract with Fairhurst following the completion of a competitive tendering procurement process through the CHEST. |