The Corporate Director Environment submitted a report seeking approval for LED lighting works to the Civic Centre, Poulton-le-Fylde and for the scheme to be included in the Council’s 2020/21 Capital Programme, funded from capital receipts.
Decision
The Resources Portfolio Holder gave approval for LED lighting works to the Civic Centre and agreed that the scheme, costing £33,820 (Including contingencies), be added to the Council’s 2020/21 Capital Programme, funded from capital receipts.
Report author: Daniel Long
Publication date: 27/03/2020
Date of decision: 27/03/2020
Decided at meeting: 27/03/2020 - Portfolio Holder Decisions
Accompanying Documents: